HAMMOCK DUNES PARKWAY AND
CAMINO DEL MAR


INTERSECTION IMPROVEMENTS
FALL 2024 – FALL 2025


PROJECT OVERVIEW

The existing four-way stop at Hammock Dunes Parkway and Camino Del Mar has been
experiencing congestion for multiple years during peak travel periods. The DCDD
has programmed this project for intersection improvements as part of ongoing
efforts to improve traffic flow. Additional lanes for turning movements will be
added along both legs of Hammock Dunes Parkway and along the eastbound leg of
Camino Del Mar. Additional bicycle facilities will be added between the
intersection and the bridge on southbound Hammock Dunes Parkway.

Download Flyer




ANTICIPATED SCHEDULE





PROJECT CONTACTS


CARLOS ROSERO, PE

Project Designer

Kisinger Campo & Associates
Email: crosero@kcaeng.com


GREG PEUGH, PE

Dunes Contact

DCDD
Email: gpeugh@dunescdd.org


MIKE WILSON

Construction Engineer

Kisinger Campo & Associates
Email: mwilson@kcaeng.com


TBD @ BID LETTING

Prime Contractor




PROJECT DATES

August 23, 2024Project Advertises for Construction BiddingSeptember 27, 2024Bids
DueLate October/Early November 2024Construction begins





Kisinger Campo & Associates Corp.