POLICY INITIATIVES

Stakeholder input is vital to the success of ISO's development and
implementation of new market designs, policies and infrastructure planning. The
policy initiative process allows for a wide variety of stakeholders to engage
and give valuable feedback through proposals, meetings, and comments, helping to
shape the future of the ISO's energy markets and operations.

To view the 2024 process timeline and policy initiative catalog, visit the
Annual policy initiatives roadmap webpage.

Learn how to use the commenting tool:

 * View presentation
 * View video

Commenting tool Recent initiative documents

--------------------------------------------------------------------------------

Miscellaneous meetings
Status: All Active Inactive Completed/Closed Print
Policy Initiatives

*Date is tentative

Title Status Proposal Development Decision Implementation Ancillary service
state of charge constraint
Joint Authority
09/19/2022ActiveNov 18, 2022 FERC approval (ER22-2881)
Sep 19, 2022 Tariff amendment (ER22-2881)
Summer 2023
Jul 01, 2023 Activation, retroactive to TD 9/20/22 (Short-term fix)
Implementation milestonesBilling, payment and credit enhancements
Joint Authority
BPC Enhancements09/26/2023ActiveSep 26, 2023 Issue paper and draft final
proposal Phase 1
Nov 08, 2023 Joint ISO Board of Governors and WEIM Governing Body
approvalCapacity procurement mechanism enhancements
Board
07/27/2022ActiveTrack 2
Sep 21, 2023 Board of Governors meeting

Track 1
Jan 11, 2023 Final proposal posted Track 1
Mar 12, 2023 Board of Governors approval
Track 1: Q3 2023*
Central procurement entity implementation
Board
11/11/2021ActiveFeb 16, 2022 Final proposal postedJul 01, 2022 FERC approval
(ER22-1604)
Apr 08, 2022 Tariff amendment filing (ER22-1604)
Mar 17, 2022 ISO Board of Governors approval
Oct 12, 2022 Master File / CIRA activation
Jan 01, 2022 Effective date for 2023 Resource Adequacy year
Implementation milestonesDay-ahead market enhancements
Joint Authority
DAME06/19/2018ActiveJul 11, 2023 Revised draft tariff language posted
May 01, 2023 Revised final proposal postedDec 20, 2023 FERC approval (ER23-2686)
Aug 22, 2023 Tariff amendment (ER23-2686)
May 17, 2023 Joint WEIM Governing Body and ISO Board of Governors approval
Oct 01, 2025 deployment
May 01, 2026 activation
Implementation milestonesDay-ahead sufficiencyDAS11/15/2023ActiveExtended
day-ahead market ISO balancing authority area participation rules
Board
EDAM ISO BAA Participation Rules03/20/2023ActiveOct 11, 2023 Revised draft
tariff language posted
Aug 15, 2023 Track A1 final proposal posted
Track A1
Nov 13, 2023 Tariff amendment (ER24-379)
Sep 21, 2023 ISO Board of Governors approval
Spring 2026
Implementation milestonesExtended day-ahead market
Joint Authority
EDAM10/03/2019ActiveMid - April 2024 EDAM access charge FERC filing

Jul 25, 2023 Revised draft tariff language posted
Dec 07, 2022 Final proposal postedDec 20, 2023 FERC approval (ER23-2686)
Aug 22, 2023 Tariff amendment (ER23-2686)
Feb 01, 2023 ISO Board of Governors and WEIM Governing Body joint approval
Oct 01, 2025 deployment
May 01, 2026 onboarding and activation
Implementation milestonesFERC Order No. 881 - managing transmission line ratings
phase 105/06/2022ActiveJun 23, 2022 Revised draft tariff language posted
Apr 20, 2023 FERC approval (ER22-2362)
Jul 12, 2022 Compliance filing (ER22-2362)
FERC Order No. 881 - managing transmission line ratings phase
205/06/2022ActiveJul 23, 2024 Working groupJun 16, 2023 Compliance Filing
(ER22-2362)
Apr 24, 2024 Data submission working group
Apr 01, 2024 - track 1
Q4 2024 - track 2
Implementation milestonesGas resource management working groupGRM working
group07/14/2023Active
Generation deliverability methodology reviewGDM12/12/2022Active
Jan 16, 2024 Initiative complete; moving to implementation
Implementation milestonesGreenhouse gas coordination working groupGHG
Coordination07/14/2023ActiveJul 29, 2024* Working group
Hybrid resources phase 2
WEIM Advisory
HR07/22/2019ActiveJan 04, 2024 Revision – Add 4 Market Simulation Business
Requirements
Sep 09, 2021 Third revised draft tariff language (phase 2b) posted
Dec 28, 2020 Revised draft tariff language (phase 2a) postedNov 30, 2021 FERC
approval (phase 2b) (ER21-2853)
Jul 15, 2021 Board of Governors approval (aggregate capability constraint)
Mar 09, 2021 FERC approval (phase 2a) (ER21-843)
Nov 18, 2020 Board of Governors approval
Nov 04, 2020 EIM Governing Body briefing

Phase 2c – RIMS: Oct 1, 2024* Activation
Phase 2c TieGen: Jul 01, 2023 Activation
Phase 2c RIMS: Q3 2023 Independent release

Phase 2b
Feb 01, 2023 Implementation

Phase 2a
Oct 01, 2021 Deployment
Oct 2021 Activation
Interconnection process enhancements 2021 phase 2
Board
IPE 202109/30/2021ActiveDec 20, 2022 Draft tariff revisions posted
Sep 20, 2022 Final proposal posted
Mar 27, 2023 FERC approval (ER23-941)
Jan 26, 2023 Tariff amendment (ER23-941)
Oct 25-26, 2022 Board of Governors approvalInterconnection process enhancements
2023 phase 1
Board
IPE02/27/2023ActiveTrack 2
Jun 25, 2024 Tariff language posted
Jul 08, 2024 Comments due
Jul 11, 2024 Meeting
Jul 2024* Track 2 FERC filing

Track 3
Jul 5, 2024 Revised straw proposal posting
Jul 15, 2024 Meeting
Jul 29, 2024 Comments due
Aug 2024* Draft final proposal posting
Sep 2024* Meeting
Sep 2024* Comments due
Oct 2024* Final proposal posting
Oct 2024* Meeting
Nov 2024* Comments due
Dec 2024* Board of Governors meeting
Track 2
Jun 12, 2024 Board of Governors approval

Track 1
Aug 01, 2023 FERC approval (ER23-2058)
Jun 02, 2023 Tariff amendment filing (ER23-2058)
May 17, 2023 Board of Governors approvalPenalty enhancements - demand response,
investigation, and tolling
Joint Authority
PEDRIT02/20/2024ActiveJul 18, 2024* Draft final proposal posting
Jul 25, 2024* Meeting
Aug 08, 2024* Comments due on draft final proposal posting
Sep 26, 2024* Joint Board of Governors and Governing Body meetingPrice formation
enhancements
Joint Authority
PFE04/11/2022ActiveMay 17, 2024 Final proposal posted
May 31, 2024 Tariff amendment filing (ER24-2168) Resource adequacy modeling and
program design RAMPD08/07/2023ActiveStorage bid cost recovery and default energy
bids enhancements06/27/2024ActiveTrack 1
Jul 18, 2024 Comments due
Jul 22, 2024 Meeting
Jul 25, 2024* Straw proposal posting
Aug 05, 2024* Meeting
Aug 08, 2024* Comments due
Aug 14, 2024* Draft final proposal posting
Aug 19, 2024* Meeting
Aug 23, 2024* Comments due
Aug 30, 2024* Final proposal posting
Sep 06, 2024* Comments due
Sep 26, 2024* Meeting
Subscriber participating transmission owner model
Board
01/11/2023ActiveJun 22, 2023 Final proposal posted
Aug 8, 2023 Revised draft tariff language posted


Jul 20, 2023 Board of Governors approvalTest V3 phase 107/18/2024ActiveTest V3
phase 207/18/2024ActiveTransmission planning process
enhancements07/14/2022Active
Transmission planning process phase 3 - revise competitive solicitation project
proposal fee05/18/2023ActiveJul 05, 2023 Final proposal and draft tariff
language posted
Jul 21, 2023 Tariff amendment filing (ER23-2464)
Jul 20, 2023 Board of Governors approval
Fall 2023*
Implementation milestonesTransmission service and market scheduling priorities
phase 2
WEIM Advisory
TSMSP05/20/2021ActiveQ1 2024* Track 2 FERC filingTrack 1
Oct 30, 2023 FERC approval (ER23-2510)
Jul 28, 2023 Tariff amendment (ER23-2510)
Feb 01, 2023 Board of Governors approval - phase 2
Monthly: Apr 17, 2024 Activation
Daily: Jun 01, 2024 Activation
Implementation milestonesVariable operations and maintenance cost review 2023
Joint Authority
VOM07/17/2023ActiveAug 23, 2023 Final proposal posted
Aug 23, 2023 Draft tariff language posted
Nov 21, 2023 FERC approval (ER23-2956)
Sep 28, 2023 Tariff amendment (ER23-2956)
Sep 20, 2023 Board of Governors approval
Dec 1, 2023 Activation
Implementation milestonesWashington WEIM greenhouse gas enhancements
Joint Authority
WA WEIM GHG Enhancements08/09/2022ActiveOct 21, 2022 Draft tariff language
posted
Sep 22, 2022 Draft final proposal postedJun 02, 2023 FERC filing (ER23-2062)
Apr 20, 2023 FERC approval of compliance filing (ER23-474)
Mar 13, 2023 Compliance filing (ER23-474)
Feb 10, 2023 FERC approval (ER23-474)
Dec 19, 2022 Motion for leave to file answer and answer (ER23-474)
Nov 21, 2022 Tariff amendment (ER23-474)
Oct 25-26, 2022 Joint ISO Board of Governors and WEIM Governing Body approval
Interim solution effective May 01, 2023
Full implementation: Nov 01, 2023
Implementation milestonesWEIM resource sufficiency evaluation enhancements
Joint Authority
RSE05/25/2021ActiveMar 21, 2023 Revised final draft tariff language posted
Nov 07, 2022 Revised final proposal postedMar 31, 2023 Tariff amendment filing
(ER23-1534)
Dec 14, 2022 Joint WEIM Governing Body and Board of Governors approval
Sep 14, 2022 FERC Order accepting compliance filing (ER22-1278)
Jun 07, 2022 Compliance filing (ER22-1278)
May 27, 2022 FERC approval (ER22-1278)
Mar 11, 2022 Tariff amendment filing (ER22-1278)
Feb 09, 2022 ISO Board of Governors approval - phase 1
Feb 02, 2022 Market Surveillance Committee opinion adopted - phase 1

Jun 01, 2022 - phase 1
Jul 01, 2023 - phase 2 track 1
Jun 2024 - phase 2 track 2

Implementation milestonesWest-wide governance pathways - step 1Pathways
Initiative06/05/2024ActiveJul 10, 2024 Comments due
Jul 23, 2024 Stakeholder callWestern EIM base schedule submission deadline phase
1
E1
BSSD09/23/2020ActiveNov 05, 2020 Draft final proposal posted
Dec 11, 2020 Revised draft tariff language posted
Sep 25, 2023 FERC approval (ER23-2505)
Jul 28, 2023 Removal of submission deadline revisions (ER23-2505/ER21-955)
Jul 19, 2023 Joint ISO Board of Governors and WEIM Governing Body approval
Apr 30, 2021 FERC approval in part/rejection in part (ER21-955)
Mar 25, 2021 Amendment to tariff changes (ER21-955)
Jan 27, 2021 Tariff amendment filing (ER21-955)
Dec 17, 2020 Board of Governors approval
Dec 02, 2020 Western EIM Governing Body approval

Phase 2:
Spring 2022 Deployment
Spring 2022 Activation

Phase 1:
May 01, 2021 Deployment
May 2021 Activation



Copyright © 2024 California Independent System Operator. All rights reserved.
Glossary Sitemap Privacy and Terms of use