 * HAM Projects
 * Project Progress Updates


HAM PROJECTS

4 LANING OF NH 544D FROM EXISTING KM 346.300 OF NH 44 (DESIGN CHAINAGE KM 0.000)
TO KM 39.380 (DESIGN CHAINAGE KM 37.000) OF ANANTAPUR – MUCHUKOTA SECTION ON
HYBRID ANNUITY MODE UNDER NH (O), IN THE STATE OF ANDHRA PRADESH

PROJECT LOCATION MAP

The Government of India had entrusted to the Authority the development,
maintenance and management of 4 Laning of NH 544D from existing Km 346.300 of NH
44 (Design Chainage Km 0.000) to Km 39.380 (Design Chainage Km 37.000) of
Anantapur – Muchukota section on Hybrid Annuity Mode under NH (O), in the state
of Andhra Pradesh. Which shall be partly financed by the Concessionaire who
shall recover its investment and costs through payments to be made by the
Authority, in accordance with the terms and conditions set forth in the
Concession Agreement entered into.

The Alignment of the project road starts at Km 0/000 of NH-544D (NH-44 near
existing Km 346.300) and runs through nearby villages namely, Somaladoddi,
Podaralla, Govindapalle, Janthuluru, Siddampeta, Bodigandidoddi, Chedulla,
Peravali, Venkatampalle and ends near Muchukota at Km 37/000 of NH-544D. The
total length of the project stretch is 36.846 Km. which runs through Anantapur.



M/s SRC Infra Developers Pvt. Ltd., has promoted and incorporated M/s SRC Infra
Anantapur - Muchukota HAM Private Limited., a limited liability company as the
Concessionaire to undertake and perform the obligations and exercise the rights
of the selected bidder under the LOA for executing the project. The Concession
Agreement (CA) between the concessionaire and NHAI was signed on 18.01.2023. The
Concessionaire has achieved Financial Closure (FC) on 05.06.2023 and the
Appointed Date was declared by the Authority as 23.07.2023.

The Concessionaire has appointed M/s SRC Infra Developers Pvt. Ltd., as the
Engineering, Procurement and Construction (EPC) Contractor and signed EPC
contract on 19.01.2023.



Global Infra Solutions Jv Artefact Projects Ltd. in association with MS
Consultant, Bhopal Support staff of IE mobilized for supervision of regular
project activities.

NHAI has appointed M/s ARMENGE Engineering Private Limited, Jaipur as the Safety
Consultant for the Project.


PROJECT OVERVIEW

Name of Work 4 Laning of NH 544D from existing Km 346.300 of NH 44 (Design
Chainage Km 0.000) to Km 39.380 (Design Chainage Km 37.000) of Anantapur –
Muchukota section on Hybrid Annuity Mode under NH (O), in the state of Andhra
Pradesh. Name of Employer National Highways Authority of India (NHAI) G-5 & 6,
Sector-10, Dwarka, New Delhi -110075 Name of Concessionaire M/s SRC Infra
Anantapur – Muchukota HAM Private Limited., Anantapuramu. Independent
Engineer/Support Staff of IE M/s Global infra-Solutions JV Artefacts Projects
LTD in Association with MS Consultant,Bhopal. EPC Contractor M/s SRC Infra
Developers Private Limited. Design Consultant M/s. Kaihatsu Design Consultants.
No.C1, Ground Floor, Chitrakut Shelters, Dasarahalli Village, K.R.Puram Hobli,
Bangalore East Taluk,Bengaluru,Karanataka-560024. Senior Lender Union Bank of
India Length of Road (DesignLength) 36.846 Kms Total Bid Project Cost Rs. 676.36
Crores (as per Concession Agreement) Date of Concession Agreement 18.01.2023
Letter of Award Date 08.12.2022 Appointed Date 23.07.2023 Scheduled Completion
Date 22.07.2025 Construction Period 730 Days (24 months)


SALIENT PROJECT FEATURES

BESIDES THE CONSTRUCTION OF NEW CARRIAGEWAYS AND WIDENING AND STRENGTHENING OF
EXISTING CARRIAGEWAYS, THE FOLLOWING TABLE SUMMARIZES THE MAJOR ELEMENTS OF THE
PROJECT CONSTRUCTION:



4 - Lane Divided Carriage Way Widening & strengthening existing 20.000 Kms New
realignment/bypass 16.846 Kms Total Length of Project 36.846 Kms Service Road/
Slip Road(LHS + RHS ) 34.060 Kms Minor Bridge 13 Nos.
(New-2+Wid-4+Reconstruction-3+Repair-4) Major Bridges 01 Nos. (across Tadakaleru
Vaagu) Light Vehicular Underpass 07 Nos. Vehicular Underpass 06 Nos. Vehicular
Over Pass Nil Culverts (Pipe & Box) 67 Nos. (5 Nos. HPC+62 Nos. Box (3-wid,
23-New and 36-Reconstruction) Major Intersections 01 Nos. Minor Intersections 20
Nos. Bus Bay & Bus Shelters 22 Nos. (18 Nos. Bus Shelters & 4 Nos. Bus Bay)
Retaining Wall (LHS + RHS) 8.402 Kms RCC lined Drain(LHS + RHS) 37.170 Kms Toll
Plaza Nil Truck Lay Bye Nil ROB Nil Project Financial Data Bid Project Cost
(INR) – (BPC) 676,36,00,000/- Performance Security submitted as per the
provisions of Concession Agreement – 3% of BPC (INR)- NHAI Policy Guidelines No:
3.1.27 dated 19.11.2020 20,29,00,000/- Payment during Construction Period (INR)
– 40% of BPC (INR) 270,54,40,000/- Bonus on early completion (Article 23.5) 0.5%
of 60% of Bid Project Cost for first 30 days.


CONTRACTUAL PROJECT MILESTONES AS PER – SCHEDULE ‘G’ OF C.A.

FOLLOWING IS A LISTING OF THE KEY PROJECT MILESTONES:

Milestone Description Target Date Milestone-I Concessionaire shall expend not
less than 20% of the Total capital cost and shall have commenced construction of
the project and achieved 20% of physical progress on 150th day from the
Appointed Date. 20.12.2023 Milestone-II Concessionaire shall expend not less
than 35% of the Total capital cost and shall have commenced construction of the
project and achieved 35% of physical progress on 330th day from the Appointed
Date. 17.06.2024 Milestone-III Concessionaire shall expend not less than 75% of
the Total capital cost and shall have commenced construction of the project and
achieved 75% of physical progress on 510th day from the Appointed Date.
14.12.2024 Scheduled Completion Date Concessionaire shall have completed the
Project on 730th day from the Appointed Date. 22.07.2025

Note: Appointed Date: 23.07.2023


SCOPE OF WORK

SCHEDULE –B, APPENDIX B VI OF CONCESSION AGREEMENT, THE PROPOSED RIGHT OF WAY
(ROW) IS OF 30 METERS,45 METERS & 60 METERS, DETAILS AS UNDER.

Sl. No. Design Chainage Length(m) Proposed ROW (m) Remarks From To 1 0+000 8+260
8260 60 2 8+260 27+700 19440 45 3 0+000 8+260 8260 60 4 27+700 33+746 6046 30 5
33+900 37+000 3100 45

The Project Highway includes the Bypasses of length 8.100 Km and Realignment
stretches of length 8.746 Km.


BYPASSES

Sl. No. Design Chainage Length(m) Location From To 1 0+000 8+100 8.100 Anantapur
Bypass Total Length in Km 8.100


REALIGNMENTS

Sl. No. Design Chainage Length(m) Location From To 1 8+700 9+100 0.400 Curve
Improvement at Rotarypuram 2 9+800 10+400 0.600 Curve Improvement near Chedulla
(near SRIT Collage) 3 14+500 15+600 1.100 Realignment at Singanmala Lake Section
4 27+700 33+746 6.046 Muchukota Reserved Forest Section 5 34+600 35+200 0.600
Curve improvement before Muchukota Village Total Length in Km 8.746

The Project includes the construction of Service Road of length 4.600 Kms and
Slip Road of length of 29.460 Kms.


SERVICE ROAD

Sl. No. Design Chainage Length(m) Side Service Road Width (m) From To 1 15+500
16+900 2.800 Both sides 7.50 2 26+300 26+800 1.000 Both side 7.50 3 26+800
27+600 0.800 Right side 7.50 Total Length in Km 4.600


SLIP ROAD

Sl. No. Design Chainage Length(m) Side Slip Road Width (m) From To 1 2+160 3+800
3.280 Both sides 7.50 2 4+500 4+820 0.640 Both sides 7.50 3 4+820 6+160 2.680
Both sides 7.50 4 7+180 10+740 7.120 Both sides 7.50 5 11+600 11+840 0.480 Both
sides 7.50 6 11+840 13+400 3.120 Both sides 7.50 7 17+720 18+600 1.760 Both
sides 7.50 8 18+600 19+000 0.800 Both sides 7.50 9 19+700 20+490 1.580 Both
sides 7.50 10 20+490 21+230 1.480 Both sides 7.50 11 23+120 23+820 1.400 Both
sides 7.50 12 24+660 25+600 1.880 Both sides 7.50 13 25+600 26+300 1.400 Both
sides 7.50 14 35+620 36+540 1.840 Both sides 7.50 Total Length in Km 29.460

Structures: The project highway involves the construction of Vehicular Underpass
(VUP), Light Vehicular Underpass (LVUP), Minor Bridges, Repair & Rectification
of existing Minor Bridges, Major Bridge and Culverts at designed locations and
same was listed as below.

Sl. No. Type Total No’s Remarks 1 VUP 06 2 LVUP 07 3 SVUP Nil 4 Vehicular
Overpass Nil 5 Major Bridge 02 01 No. New construction & 01 No. Repair /
Rehabilitation 6 Minor Bridge Reconstruction 03 New Construction 02 Widening 04
Repairs 04 7 Culverts Widening of Hump Pipe Culvert 05 Reconstruction of Box
Culvert 36 New Construction of Box Culverts 23 Widening of Box Culvert 03


INTERSECTIONS:

Sl.No Type Total No’s Remarks 1 Major Intersections 01 No’s 2 Minor
Intersections 20 No’s


PROJECT FACILITIES:

Sl.No Type of Facility Total Remarks 1 Toll Plazas Nil 2 Road Side Furniture i)
Traffic Signs Includes Roadside signs, Overhead Signs, Kerb Mounted Signs, etc.
Shall be prepared as per the Manual requirements. ii) Overhead Signs iii)
Pavement Marking Entire Project Highway As per Manual requirements. iv) LED
Traffic Beacons Entire Project Highway As per Manual requirements v) Cat’s Eye /
Road Studs Horizontal Curve below 700m, median opening, intersections, Cross
roads & Built-up areas and shall confirm to the specifications mentioned in
Schedule D. vi) Delineators As per IRC 79 – 1981 and Schedule – D. vii)
Hectometre / Kilometre Stones Entire Project Highway As per Manual requirements.
viii) Safety Barrier W – Beam = 78.062 Km (all sides inclusive). MS railing as
per TCS and manual requirements. ix) Boundary Wall Provided on both side of ROW
available of Project Highway 3 Highway Lighting Bus bays and shelter,
Interchange with all Ramps, Grade separators including slip roads, built up
sections, Major Bridge and At Grade Junctions. Solar Lighting at Junctions,
interchanges with all Ramps. 4 Pedestrian Facilities As per Manual 5 Bus bays
and Bus Shelters 22 Nos 4 Bus Bay & 18 Bus Shelters. 6 Landscaping and Tree
Plantation i) Tree Plantation 8780 Nos. As per the provisions of IRC SP – 21 and
Manual requirements. ii) Median openings 04 Nos As per Manual. iii) Landscaping
and tree plantation Including but not limited to the following – Grade Separated
Intersections, Entry and Exit Ramps, At grade islands of intersection
locations.Road Side, Bus bays on both sides of ROW, any other location as per
requirements of Clause 11.3 of Manual. 7 Traffic Aid Posts Nil 8 Medical Aid
Posts Nil 9 Vehicle Rescue Posts Nil 10 Utility Crossing / duct As per manual 11
Others i) Advanced Traffic Management System (ATMS) As per Manual